9 - Replace the Circuit Breakers and terminals
10 - Replace Relays and relay terminals (improved connection over oxidized connections)
11 - Replace wiring connections at tail light circuit boards (with new improved connectors)
12 - Troubleshoot/replace windshield washer pump
13 - Figure out why rear view mirror is so loose
14 - Fix the center console clock
15 - Finish installing cold air intake ducting (removed heat stove pipe) -Done
16 - Replace Fuse Box (recommeded due to undersized contact terminals - two of mine are melted) 
17 - Install Stainless Steel Coolant Bottle
18 - Install new Parking Break Pads -Done
posted by Charles at 12:39 PM 0 comments

Monday, January 14, 2008

Tons to do when it gets nice out.

I have a ton to do to the D, I just haven't had the time and when I do it to freaking cold out. (I hate working on cars in the cold btw)

Since the weather is improving some (that is until I heard were supposed to get 3-5" of snow tuesday night) I thought I would make a list of things to do when the weather does improve.
(no real order)

1 - Put on rear fascia stainless letters (needs to be Warm out) -Done
2 - Install new parking brake switch -Done
3 - install new arm rest bolster caps - I'll explain later
4 - Install new Angle Drive - no wait, I don't have it yet - its still on back order form 5 months ago!!  DMC get it together!  I might just have to build my own angle drive. 
5 - Install new power antenna -Done
6 - Finish the wiring for my Remote trunk release.
7 - Fix speaker wires at the back of the radio - it cuts out when ever I go over a bump. - Very annoying!
8 - Fix AC system (suspect electrical issue at multi-switch)
9- There is more - I update this as  I think of it.